SUPCON Wins Recognition in the commissioning of Xinjiang Hesheng Power 2×350MW Supercritical Turbine Unit Integrated Control Project
Release time:Oct 09, 2018

Xinjiang Hesheng Power 2×350MW Supercritical Turbine Unit Integrated Control Project announced successful commissioning last month. SUPCON received favorable feedback from the end user.

 

The Unit adopts 2×1200t/h pulverized coal boiler for the 2×350MW Supercritical steam turbine unit. As a typical digital power plant, the control solution integrates the main engine DCS (DAS, MCS, SCS, FSSS, ECS), ETS, DEH, MEH, METS, and the auxiliary engine DCS (coal feeding, desulfuration, dedusting, denitration). The project contains 33,000 I/O points, 97 pairs of controllers, 150 cabinets, 5 engineer stations, 42 operator stations.